The Fibreglass Pool Renovation in Drummoyne was completed in 2.5 weeks, despite several challenges. The pool, measuring 7.5m x 3m, was covered in osmosis, which required additional work. Our team had to grind and bog multiple areas to repair the damaged surface before proceeding with the resurfacing. Furthermore, the renovation faced interruptions due to wet weather. However, our team quickly resolved the issue by building a weather protection system. We created a tarp/tent structure over the pool, allowing the work to continue without significant delays.

We started the Fibreglass Pool Renovation by draining the pool and preparing the surface for repairs. Due to the extensive osmosis, we performed multiple grinding and bogging procedures to smooth out the surface and ensure a proper base for the fibreglass laminate. Although the weather posed difficulties, our team’s swift action in setting up weather protection allowed us to stay on schedule.

Once the osmosis treatment was complete, we applied a primer coat to strengthen the pool’s surface. We followed this by applying the fibreglass laminate, which reinforced the structure and added durability. Next, we applied the bulk resin coat to seal the fibreglass and enhance the pool’s longevity. Afterward, the team added the filler coat and the final topcoat, which provided a smooth and attractive finish.

Finally, we ensured that the step treads had a non-slip surface for safety, and we replaced the hydrostatic valve to complete the renovation. Despite the challenges of osmosis and wet weather, the Fibreglass Pool Renovation in Drummoyne was finished within the expected timeframe, delivering a fully restored and functional pool.

service image project images after
service image service image

About Project

This Fibreglass Pool Renovation in Drummoyne presented several unique challenges. The pool, which measured 7.5m x 3m, was heavily affected by osmosis. This required extra work, including grinding and bogging the surface to repair the damage. Our team had to ensure the pool was smooth and stable before applying the fibreglass laminate. Additionally, persistent wet weather threatened to delay the project. However, our team quickly devised a solution by building a tarp/tent structure over the pool. This weather protection allowed us to proceed with the work without interruption. After resolving the osmosis issues, we applied a primer coat, followed by the fibreglass laminate, to reinforce the pool’s structure. The bulk resin coat was applied next to further enhance the pool’s durability. Finally, we applied a filler coat and a topcoat to give the pool a smooth, polished finish. Despite the challenges, we completed the project in 2.5 weeks, restoring the pool to perfect condition.

For this project, we followed the following process:

  1. Drain the pool.
  2. Remove hydrostatic valve and brace pool.
  3. Prepare pool surface to accommodate new fibreglass interior.
  4. Cut out and treat osmosis.
  5. Apply Primer Coat.
  6. Apply Reinforcing Material (Fibreglass Laminate)
  7. Apply Bulk Resin Coat over Fibreglass Laminate
  8. Apply Filler Coat (undercoat)
  9. Apply Final Topcoat (colour of your choice)
  10. Apply a non-slip surface to step treads
  11. Replace hydrostatic valve.